+Pull request reviewing process
+==============================
+
+# Labels
+
+Labels are carefully picked to optimize for:
+
+ - Readability: maintainers must immediately know the state of a PR
+ - Filtering simplicity: different labels represent many different aspects of
+   the reviewing work, and can even be targetted at different maintainers groups.
+
+A pull request should only be attributed labels documented in this section: other labels that may
+exist on the repository should apply to issues.
+
+## DCO labels
+
+ * `dco/no`: automatically set by a bot when one of the commits lacks proper signature
+
+## Status labels
+
+ * `status/0-triage`
+ * `status/1-design-review`
+ * `status/2-code-review`
+ * `status/3-docs-review`
+ * `status/4-ready-to-merge`
+
+Special status labels:
+
+ * `status/needs-attention`: calls for a collective discussion during a review session
+
+## Specialty group labels
+
+Those labels are used to raise awareness of a particular specialty group, either because we need
+help in reviewing the PR, or because of the potential impact of the PR on their work:
+
+ * `group/distribution`
+ * `group/networking`
+ * `group/security`
+ * `group/windows`
+
+## Impact labels (apply to merged pull requests)
+
+ * `impact/api`
+ * `impact/changelog`
+ * `impact/cli`
+ * `impact/dockerfile`
+ * `impact/deprecation`
+
+# Workflow
+
+An opened pull request can be in 1 of 5 distinct states, for each of which there is a corresponding
+label that needs to be applied.
+
+## Triage - `status/0-triage`
+
+Maintainers are expected to triage new incoming pull requests by removing the `status/0-triage`
+label and adding the correct labels (e.g. `status/1-design-review`) before any other interaction
+with the PR. The starting label may potentially skip some steps depending on the kind of pull
+request: use your best judgement.
+
+Maintainers should perform an initial, high-level, overview of the pull request before moving it to
+the next appropriate stage:
+
+ - Has DCO
+ - Contains sufficient justification (e.g., usecases) for the proposed change
+ - References the Github issue it fixes (if any) in the commit or the first Github comment
+
+Possible transitions from this state:
+
+ * Close: e.g., unresponsive contributor without DCO
+ * `status/1-design-review`: general case
+ * `status/2-code-review`: e.g. trivial bugfix
+ * `status/3-docs-review`: non-proposal documentation-only change
+
+## Design review - `status/1-design-review`
+
+Maintainers are expected to comment on the design of the pull request.  Review of documentation is
+expected only in the context of design validation, not for stylistic changes.
+
+Ideally, documentation should reflect the expected behavior of the code.  No code review should
+take place in this step.
+
+There are no strict rules on the way a design is validated: we usually aim for a consensus,
+although a single maintainer approval is often sufficient for obviously reasonable changes. In
+general, strong disagreement expressed by any of the maintainers should not be taken lightly.
+
+Once design is approved, a maintainer should make sure to remove this label and add the next one.
+
+Possible transitions from this state:
+
+ * Close: design rejected
+ * `status/2-code-review`: general case
+ * `status/3-docs-review`: proposals with only documentation changes
+
+## Code review - `status/2-code-review`
+
+Maintainers are expected to review the code and ensure that it is good quality and in accordance
+with the documentation in the PR.
+
+New testcases are expected to be added. Ideally, those testcases should fail when the new code is
+absent, and pass when present. The testcases should strive to test as many variants, code paths, as
+possible to ensure maximum coverage.
+
+Changes to code must be reviewed and approved (LGTM'd) by a minimum of two code maintainers. When
+the author of a PR is a maintainer, he still needs the approval of two other maintainers.
+
+Once code is approved according to the rules of the subsystem, a maintainer should make sure to
+remove this label and add the next one. If documentation is absent but expected, maintainers should
+ask for documentation and move to status `status/3-docs-review` for docs maintainer to follow.
+
+Possible transitions from this state:
+
+ * Close
+ * `status/1-design-review`: new design concerns are raised
+ * `status/3-docs-review`: general case
+ * `status/4-ready-to-merge`: change not impacting documentation
+
+## Docs review - `status/3-docs-review`
+
+Maintainers are expected to review the documentation in its bigger context, ensuring consistency,
+completeness, validity, and breadth of coverage across all existing and new documentation.
+
+They should ask for any editorial change that makes the documentation more consistent and easier to
+understand.
+
+Changes and additions to docs must be reviewed and approved (LGTM'd) by a minimum of two docs
+sub-project maintainers. If the docs change originates with a docs maintainer, only one additional
+LGTM is required (since we assume a docs maintainer approves of their own PR).
+
+Once documentation is approved (see below), a maintainer should make sure to remove this label and
+add the next one.
+
+Possible transitions from this state:
+
+ * Close
+ * `status/1-design-review`: new design concerns are raised
+ * `status/2-code-review`: requires more code changes
+ * `status/4-ready-to-merge`: general case
+
+## Merge - `status/4-ready-to-merge`
+
+Maintainers are expected to merge this pull request as soon as possible. They can ask for a rebase
+or carry the pull request themselves.
+
+Possible transitions from this state:
+
+ * Merge: general case
+ * Close: carry PR
+
+After merging a pull request, the maintainer should consider applying one or multiple impact labels
+to ease future classification:
+
+ * `impact/api` signifies the patch impacted the remote API
+ * `impact/changelog` signifies the change is significant enough to make it in the changelog
+ * `impact/cli` signifies the patch impacted a CLI command
+ * `impact/dockerfile` signifies the patch impacted the Dockerfile syntax
+ * `impact/deprecation` signifies the patch participates in deprecating an existing feature
+
+## Close
+
+If a pull request is closed it is expected that sufficient justification will be provided. In
+particular, if there are alternative ways of achieving the same net result then those needs to be
+spelled out. If the pull request is trying to solve a use case that is not one that we (as a
+community) want to support then a justification for why should be provided.
+
+The number of maintainers it takes to decide and close a PR is deliberately left unspecified. We
+assume that the group of maintainers is bound by mutual trust and respect, and that opposition from
+any single maintainer should be taken into consideration. Similarly, we expect maintainers to
+justify their reasoning and to accept debating.
+
+# Escalation process
+
+Despite the previously described reviewing process, some PR might not show any progress for various
+reasons:
+
+ - No strong opinion for or against the proposed patch
+ - Debates about the proper way to solve the problem at hand
+ - Lack of consensus
+ - ...
+
+All these will eventually lead to stalled PR, where no apparent progress is made across several
+weeks, or even months.
+
+Maintainers should use their best judgement and apply the `status/needs-attention` label. It must
+be used sparingly, as each PR with such label will be discussed by a group of maintainers during a
+review session. The goal of that session is to agree on one of the following outcomes for the PR:
+
+ * Close, explaining the rationale for not pursuing further
+ * Continue, either by pushing the PR further in the workflow, or by deciding to carry the patch
+   (ideally, a maintainer should be immediately assigned to make sure that the PR keeps continued
+   attention)
+ * Escalate to Solomon by formulating a few specific questions on which his answers will allow